Project Details:

Project: Newark Recycling Center

Location: Newark, DE

Duration: April 2020 – July 2020

Client: Delaware Solid Waste Authority

Project Details:

Diamond Materials completed the Newark Recycling Drop Off Center for the Delaware Solid Waste Authority. This is Diamond's first project and partnership with the Delaware Solid Waste Authority. For hours and a list of accepted items,

please visit: https://dswa.com/facilities/newark-recycling-center/

Work Performed:

Topsoil stripped: 2500 CY
Cuts to fills: 2060 CY
Storm sewer: 2605 LF
Sanitary sewer: 434 LF
Waterline: 342 LF
Paving: 2245 tons
6” Thick Concrete Pads 600 SF
Excavate and install 3940SF Bio-retention pond
Installation of a 1175 LF Chain Link Fence, Installation of 297 LF Ornamental Fence, 3 Drainage Inlets, 1 wet tap. Installed 3 Custom Flag Poles